Introducing a utility transformer project tailored for the Thailand。 This utility initiative requires 215 units of single-phase pad-mounted transformers, all UL listed, including 175 units of 25 kVA and 40 units of 50 kVA.
The end user's project timeline is 90 days. Adherence to IEEE standards is imperative for single-phase transformers. Additionally, the design of transformer components and markings must be customized to meet project specifications.
25 kVA Single Phase Pad Mounted Transformer
- Primary Voltage(V): 12470GRDY/7200
- Secondary Voltage(V): 240/120
- Frequency: 60Hz
- Polarity: Additive
- Impedance: ≤1.5%
- Altitude: ≤1000
- Winding Material: Aluminum
- Efficiency: As per DOE
- Tank & Accessories Weight: 170Kg
- Total Oil Weight: 200L
- Total Weight: 470Kg
50 kVA Single Phase Pad Mounted Transformer
- Primary Voltage(V): 12470GRDY/7200
- Secondary Voltage(V): 240/120
- Frequency: 60Hz
- Polarity: Additive
- Impedance: ≤2%
- Altitude: ≤1000
- Winding Material: Aluminum
- Efficiency: As per DOE
- Tank & Accessories Weight: 180Kg
- Total Oil Weight: 200L
- Total Weight: 520Kg
Transformer Testing
Upon completing production, GNEE conducted Factory Acceptance Tests (FAT) for each transformer, including ratio, polarity, and phase relation tests, resistance tests, applied and induced potential tests, loss tests, leak tests, and operation tests for all devices.